You are viewing: Why Projects Fail? Part 2
By Simon Buehring

Why Projects Fail? Part 2

Articles - Business - Management - View Article



Publish this article

"Directing a Successful Project": the C-NOMIS case study

(This is part 2 of a series of 10 posts: Why projects fail?)

This post deals with the second of the OGC's eight causes of project failure: the lack of effective or clear senior management, ownership or leadership at higher levels within the organisation.

The PRINCE2 project management methodology recognises 4 levels of project-related management:

* Team manager (ground-level operations)
* Project manager (manages the day-to-day project decisions)
* Project board (responsible for decisions outside the project manager's scope, for example, dealing with exceptional risks or requests for change)
* Programme/corporate management (responsible for the integration of the project into the wider programme or business strategy)

The final management level actually falls outside of project management, but effective programme/corporate management is crucial for ensuring that a project makes coherent business sense.

According to the NAO report, the C-NOMIS project has been overseen by three different SROs (Senior Responsible Officers), the first of whom had very little prior experience working with large-scale IT systems projects. A further element of confusion was added by the fact that NOMS - the organisation running the project - was a recent amalgamation of HM Prisons, the National Probation Service and various other government offices and organisations, all of which came with their own management structures and their own ways of doing things.

The consequences of this confusion were as follows:

* Poor monitoring by senior management

Neither the project board nor the SRO requested or received any information about the project beyond standard summaries and briefings until mid-2007. There is no evidence during this period that senior management monitored the delivery of the product.
* No clear financial accountability

Although the project board met once every two months, the records show that there was no discussion of project finances until May 2007 - by which point the estimated cost of the project had almost tripled to £690 billion.
* Weak change control

One key reason for the increasing costs and delays was the "scope creep" allowed on the final product (the integrated database). This was partly caused by having various requirements from the different departments and no central figure of authority to ensure that the requirements were compatible, achievable and necessary to the project objectives. Scope creep can be fatal for a project in the Business Case is not regularly reviewed, as it changes the cost/benefit balance - often for the worse.

Summary and solutions

The newly-updated PRINCE2 guidance includes the release of a PRINCE2 manual aimed particularly at senior managers, who need to understand the basics of the PRINCE2 method and their PRINCE2 responsibilities. This manual is called Directing a Project, and may eventually lead to an additional qualification particular to project board members. You may learn more details about how projects should be directed by attending PRINCE2 training.

The MSP programme management methodology and certification is also an invaluable source of best-practice guidance for individuals new to senior project management roles and responsibilities.
Looking ahead ...

The lack of clear senior management, leadership and ownership on the project was a key factor in the failure of C-NOMIS. In my next post I am going to look at the third of the causes of project failure - no effective stakeholder engagement.

See All articles From Author

Simon Buehring is a project manager, consultant and trainer. He works for KnowledgeTrain which offers PRINCE2 courses in the UK and overseas. Simon has extensive experience within the IT industry in the UK and Asia. He can be contacted via the KnowledgeTrain project management course website.

Article Source : http://www.articlecontentking.com

Tags: project failure prince2 training

Word Count Appx. : 525 | Article Views 462 Published 29-11-2009


Related articles
Japanese Companies Joining War for Global Talent (Part 1)
By: Megumi Oyanagi | 16-12-2011

This is about how Japanese companies started to strategically acquire, develop and retain/engage global talent, when they have been behind their western counterparts in this area. This is because they need to globalize their organization and business (read entire article)

Measuring Performance - The Key to Improvement
By: Jack Norris | 06-04-2011

Utilise vehicle tracking technology to measure the performance of your mobile fleet and make adjustments to improve efficiency.

(read entire article)
Comparison Between Manual and Computerized Accounting
By: Adeline Mary | 25-01-2010

Accounting is a fundamental slogan of every business. Without the accounting practice, it is difficult to be effective in your business. Its basically helps you to monitor the transactions happening in the business.

(read entire article)
How to Choose Project Management Software
By: Groshan Fabiola | 06-11-2008
In todays business environment everyone needs Project Management tools. And professionals who manage Projects are called Project Managers (read entire article)
ISO 21500, the New Frontier for Programme and Project Management
By: John Thorpe | 17-07-2009
Currently there are a range of publications under the flag of BS 6079 which offer guidance in the field of project management. BS 6079-1:2002 describes a full range of project management procedures, techniques and tools that the user can select as appr (read entire article)
Open Plan vs Closed Office Space
By: Anna Norman-Butler | 11-12-2010

How you want the space configured? Is one of the first questions your landlord, or serviced office operator will ask when moving into a new office space. This article outlines the benefits and drawback of both Open plan and Closed Office Space.

(read entire article)
Win Your Life Back - 6 Steps to Work Smart and Increase Your Free Time in the Restaur
By: Tony Rodono | 25-04-2011

Too many restaurant operators needlessly end up hating the career they once enjoyed. The good news: They can turn it all around, today. And you can too!

(read entire article)
Vocational Success Why we need to write down our procedures.
By: Morgan F Bryan | 07-02-2009
The value of establishing written procedures (read entire article)
Are You Missing Your Best Quality Improvement Ideas?
By: Donald Bryant | 03-09-2011

November 2005. Winter is just around the corner here in Western Michigan. The leaves are literally raining off the trees. Just this morning at breakfast as I looked into the woods and I could see a steady stream of golden brown, red and yel

(read entire article)